Vertical Concrete Elements Striking Times: Maturity method and Uruguay Survey

Tiempos de desencofrado de elementos verticales de hormigón armado: método a través de coeficientes de maduración y encuesta en Uruguay

Rudeli, Natalia - Santilli, Adrián
Detalles Bibliográficos
2014
Desencofrado
Maduración
Elementos verticales de hormigón
Formwork
Maturity
Vertical concrete elements
Español
Universidad de Montevideo
REDUM
http://revistas.um.edu.uy/index.php/ingenieria/article/view/348
Acceso abierto
Atribución 4.0 Internacional
_version_ 1811886514996510720
author Rudeli, Natalia
author2 Santilli, Adrián
author2_role author
author_facet Rudeli, Natalia
Santilli, Adrián
author_role author
collection REDUM
dc.creator.none.fl_str_mv Rudeli, Natalia
Santilli, Adrián
dc.date.none.fl_str_mv 2014-11-27
dc.description.en-US.fl_txt_mv For the construction of vertical concrete elements temporary structures called formwork are used. Their use represents one of the higher cost that construction companies has affront and in some cases may rise up to 60% of the total cost of the concrete. In this article the results of a survey realized to more than 100 construction-related people are shown, where it can be concluded the ignorance on optimal times striking times issue. In general, the striking mechanism and timing are arbitrarily determined and non-methodology is used to determine them. Additionally, a methodology is presented to determine the striking time of vertical concrete elements by the use of the maturity method that takes into account temperature variations along the filling and striking period. This methodology allows predicting the minimum striking time regardless of the type of concrete used, through the continuous measurement of the maturity coefficients in situ.
dc.description.es-ES.fl_txt_mv Para la construcción de elementos verticales de hormigón se emplean estructuras temporales denominadas encofrados. Su utilización representa uno de los mayores costos que deben afrontar las empresas constructoras y que puede ascender hasta un 60% del costo total del hormigón. En este artículo se muestran los resultados de una encuesta realizada a más de 100 personas relacionadas con la construcción, donde se puede concluir el amplio desconocimiento en el tema de tiempos óptimos de desencofrado. En general, el mecanismo y los tiempos de desencofrado son decididos arbitrariamente y no se utiliza una metodología para determinarlos. Adicionalmente, se presenta una metodología para determinar el tiempo de desencofrado de elementos verticales de hormigón a partir de la utilización del método de los Coeficientes deMaduración que toma en cuenta las variaciones de temperatura a lo largo del período comprendido entre el llenado y el desencofrado. Esta metodología permite predecir el tiempo mínimo de desencofrado independientemente del tipo de hormigón utilizado, a partir de lamedición continua de los coeficientes de maduración del hormigón en obra.
dc.format.none.fl_str_mv application/pdf
dc.identifier.none.fl_str_mv http://revistas.um.edu.uy/index.php/ingenieria/article/view/348
dc.language.iso.none.fl_str_mv spa
dc.publisher.es-ES.fl_str_mv Universidad de Montevideo
dc.relation.none.fl_str_mv http://revistas.um.edu.uy/index.php/ingenieria/article/view/348/418
dc.rights.es-ES.fl_str_mv Derechos de autor 2019 Natalia Rudeli, Adrián Santilli
http://creativecommons.org/licenses/by/4.0
dc.rights.license.none.fl_str_mv Atribución 4.0 Internacional
dc.rights.none.fl_str_mv info:eu-repo/semantics/openAccess
dc.source.en-US.fl_str_mv Memoria Investigaciones en Ingeniería; No. 12 (2014); 45-55
dc.source.es-ES.fl_str_mv Memoria Investigaciones en Ingeniería; Núm. 12 (2014); 45-55
dc.source.none.fl_str_mv 2301-1106
2301-1092
reponame:REDUM
instname:Universidad de Montevideo
instacron:Universidad de Montevideo
dc.source.pt-BR.fl_str_mv Memoria Investigaciones en Ingenieria; n. 12 (2014); 45-55
dc.subject.en-US.fl_str_mv Formwork
Maturity
Vertical concrete elements
dc.subject.es-ES.fl_str_mv Desencofrado
Maduración
Elementos verticales de hormigón
dc.title.none.fl_str_mv Vertical Concrete Elements Striking Times: Maturity method and Uruguay Survey
Tiempos de desencofrado de elementos verticales de hormigón armado: método a través de coeficientes de maduración y encuesta en Uruguay
dc.type.en-US.fl_str_mv Peer reviewed articles
dc.type.es-ES.fl_str_mv Artículos evaluados por pares
dc.type.none.fl_str_mv info:eu-repo/semantics/article
info:eu-repo/semantics/publishedVersion
dc.type.pt-BR.fl_str_mv Artigos revistos por pares
dc.type.version.none.fl_str_mv publishedVersion
info:eu-repo/semantics/publishedVersion
description For the construction of vertical concrete elements temporary structures called formwork are used. Their use represents one of the higher cost that construction companies has affront and in some cases may rise up to 60% of the total cost of the concrete. In this article the results of a survey realized to more than 100 construction-related people are shown, where it can be concluded the ignorance on optimal times striking times issue. In general, the striking mechanism and timing are arbitrarily determined and non-methodology is used to determine them. Additionally, a methodology is presented to determine the striking time of vertical concrete elements by the use of the maturity method that takes into account temperature variations along the filling and striking period. This methodology allows predicting the minimum striking time regardless of the type of concrete used, through the continuous measurement of the maturity coefficients in situ.
eu_rights_str_mv openAccess
format article
id REDUM_4eada7a514ce9de736b70d4d94a3a28d
instacron_str Universidad de Montevideo
institution Universidad de Montevideo
instname_str Universidad de Montevideo
language spa
network_acronym_str REDUM
network_name_str REDUM
oai_identifier_str oai:redum.um.edu.uy:20.500.12806/2503
publishDate 2014
reponame_str REDUM
repository.mail.fl_str_mv nolascoaga@um.edu.uy
repository.name.fl_str_mv REDUM - Universidad de Montevideo
repository_id_str 10501
rights_invalid_str_mv Derechos de autor 2019 Natalia Rudeli, Adrián Santilli
http://creativecommons.org/licenses/by/4.0
Atribución 4.0 Internacional
spelling Rudeli, NataliaSantilli, Adrián2014-11-27http://revistas.um.edu.uy/index.php/ingenieria/article/view/348For the construction of vertical concrete elements temporary structures called formwork are used. Their use represents one of the higher cost that construction companies has affront and in some cases may rise up to 60% of the total cost of the concrete. In this article the results of a survey realized to more than 100 construction-related people are shown, where it can be concluded the ignorance on optimal times striking times issue. In general, the striking mechanism and timing are arbitrarily determined and non-methodology is used to determine them. Additionally, a methodology is presented to determine the striking time of vertical concrete elements by the use of the maturity method that takes into account temperature variations along the filling and striking period. This methodology allows predicting the minimum striking time regardless of the type of concrete used, through the continuous measurement of the maturity coefficients in situ.Para la construcción de elementos verticales de hormigón se emplean estructuras temporales denominadas encofrados. Su utilización representa uno de los mayores costos que deben afrontar las empresas constructoras y que puede ascender hasta un 60% del costo total del hormigón. En este artículo se muestran los resultados de una encuesta realizada a más de 100 personas relacionadas con la construcción, donde se puede concluir el amplio desconocimiento en el tema de tiempos óptimos de desencofrado. En general, el mecanismo y los tiempos de desencofrado son decididos arbitrariamente y no se utiliza una metodología para determinarlos. Adicionalmente, se presenta una metodología para determinar el tiempo de desencofrado de elementos verticales de hormigón a partir de la utilización del método de los Coeficientes deMaduración que toma en cuenta las variaciones de temperatura a lo largo del período comprendido entre el llenado y el desencofrado. Esta metodología permite predecir el tiempo mínimo de desencofrado independientemente del tipo de hormigón utilizado, a partir de lamedición continua de los coeficientes de maduración del hormigón en obra.application/pdfspaUniversidad de Montevideohttp://revistas.um.edu.uy/index.php/ingenieria/article/view/348/418Derechos de autor 2019 Natalia Rudeli, Adrián Santillihttp://creativecommons.org/licenses/by/4.0info:eu-repo/semantics/openAccessAtribución 4.0 InternacionalMemoria Investigaciones en Ingeniería; No. 12 (2014); 45-55Memoria Investigaciones en Ingeniería; Núm. 12 (2014); 45-55Memoria Investigaciones en Ingenieria; n. 12 (2014); 45-552301-11062301-1092reponame:REDUMinstname:Universidad de Montevideoinstacron:Universidad de MontevideoDesencofradoMaduraciónElementos verticales de hormigónFormworkMaturityVertical concrete elementsVertical Concrete Elements Striking Times: Maturity method and Uruguay SurveyTiempos de desencofrado de elementos verticales de hormigón armado: método a través de coeficientes de maduración y encuesta en Uruguayinfo:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionPeer reviewed articlesArtículos evaluados por paresArtigos revistos por parespublishedVersioninfo:eu-repo/semantics/publishedVersion20.500.12806/25032024-10-01 12:10:11.255oai:redum.um.edu.uy:20.500.12806/2503Universidadhttps://um.edu.uy/https://redum.um.edu.uy/oai/requestnolascoaga@um.edu.uyUruguayopendoar:105012024-10-01T15:10:11REDUM - Universidad de Montevideofalse
spellingShingle Vertical Concrete Elements Striking Times: Maturity method and Uruguay Survey
Rudeli, Natalia
Desencofrado
Maduración
Elementos verticales de hormigón
Formwork
Maturity
Vertical concrete elements
status_str publishedVersion
title Vertical Concrete Elements Striking Times: Maturity method and Uruguay Survey
title_full Vertical Concrete Elements Striking Times: Maturity method and Uruguay Survey
title_fullStr Vertical Concrete Elements Striking Times: Maturity method and Uruguay Survey
title_full_unstemmed Vertical Concrete Elements Striking Times: Maturity method and Uruguay Survey
title_short Vertical Concrete Elements Striking Times: Maturity method and Uruguay Survey
title_sort Vertical Concrete Elements Striking Times: Maturity method and Uruguay Survey
topic Desencofrado
Maduración
Elementos verticales de hormigón
Formwork
Maturity
Vertical concrete elements
url http://revistas.um.edu.uy/index.php/ingenieria/article/view/348